Key facts
- Loan to cost (LTC)
- Facility limit divided by total development cost
- GRV LVR
- Facility limit divided by gross realisable value
- Facility size
- The lower of the LTC and GRV results
- Qualifying presale
- Unconditional, arm's length, deposit held
- APRA presale minimum
- None. Confirmed by APRA in February 2025
How do lenders size a development finance facility?
Lenders size a development finance facility by applying two limits to your project, loan to cost and loan to gross realisable value, and lending the lower of the two results. A presale condition may then decide when, or whether, the construction money can be drawn.
This guide supports the main development finance page and goes deeper on the three numbers that shape every approval. All percentages are typical market practice as at November 2026 and vary by lender. None of them is set by law.
What is loan to cost (LTC)?
Loan to cost (LTC) is the facility limit divided by the total development cost of the project. Lenders also call it the loan to cost ratio (LCR) or loan to development cost (LDC).
Total development cost normally includes:
- land, at purchase price or current valuation, plus stamp duty and acquisition costs
- the building contract sum and any separate civil works
- consultant, design and project management fees
- council, authority and infrastructure contributions
- a contingency allowance
- finance costs: capitalised interest, establishment and line fees, valuation and quantity surveyor fees
- selling and marketing costs, where the lender allows them in the budget
As a general guide, many banks lend around 65 to 80 per cent of total development cost, and some non-bank lenders go higher for a higher margin. The remainder is your equity. LTC is the lender's check that you have enough of your own money at risk, which is why it will question a land value that sits well above what you paid.
What is the GRV LVR?
The GRV LVR is the facility limit divided by the gross realisable value (GRV) of the project, which is the valuer's estimate of the total proceeds if every lot sold on completion in the current market. It is the development version of the loan to value ratio used for a standing property, explained in the guide to commercial property loan deposits and LVR.
Most lenders measure GRV net of GST, and some also deduct selling costs to reach a net realisable value. As a general guide, many lenders work in a range of about 60 to 70 per cent of net GRV. Always ask which definition a lender uses, because 65 per cent of a GST-inclusive figure is a larger loan than 65 per cent of a net figure.
The GRV LVR is the lender's check on the exit. It shows how far prices could fall before the sale proceeds no longer repay the debt.
| Measure | Loan to cost (LTC) | GRV LVR |
|---|---|---|
| Formula | Facility limit divided by total development cost | Facility limit divided by gross realisable value |
| Risk it tests | Whether the developer has enough equity at risk | Whether end values cover the debt if prices fall |
| Who sets the base figure | Your feasibility, checked by the quantity surveyor | The lender's valuer |
| Typical range (general guide) | 65 to 80 per cent | 60 to 70 per cent of net GRV |
| Tends to be the binding limit when | The profit margin is high | The profit margin is thin |
How do LTC and GRV limits work together in a worked example?
LTC and GRV limits work together as a "lower of" test: the lender calculates a maximum loan under each and offers the smaller amount. The example below is illustrative only, uses round numbers and is not a quote.
Assume a project of 10 townhouses with a total development cost of $8.0 million and a GRV of $10.0 million net of GST ($1.0 million per townhouse). The lender's limits are 75 per cent LTC and 65 per cent GRV LVR.
| Item | Base case | Valuer adopts a lower GRV |
|---|---|---|
| Total development cost | $8,000,000 | $8,000,000 |
| GRV, net of GST | $10,000,000 | $9,000,000 |
| Maximum loan at 75 per cent LTC | $6,000,000 | $6,000,000 |
| Maximum loan at 65 per cent GRV LVR | $6,500,000 | $5,850,000 |
| Facility offered (lower of the two) | $6,000,000 | $5,850,000 |
| Equity required | $2,000,000 | $2,150,000 |
In the base case the LTC limit binds and you contribute $2.0 million. If the valuer's GRV comes in 10 per cent below your feasibility, the GRV limit takes over and you need another $150,000 before the first drawdown. The valuation is outside your control, so hold a cash buffer until it is finalised.
The facility limit includes capitalised interest and fees. The $6.0 million is the peak debt, not the amount available for the builder, and the way it is drawn is covered in the guide to construction finance.
What is a qualifying presale?
A qualifying presale is a contract of sale for a lot in the project that meets the lender's own tests for being likely to settle. Lenders count only qualifying presales toward a presale condition, so a contract your agent calls a sale may not count.
Each lender writes its own definition. Common requirements are:
- an unconditional, exchanged contract on the lender's approved form
- an arm's length purchaser who is not related to the developer or builder
- a deposit, commonly 10 per cent, held in a trust account, with some lenders accepting deposit bonds or bank guarantees
- a sunset date that leaves a comfortable margin after the forecast completion date
- a price in line with the valuation, with any rebates or incentives disclosed
- limits on the number of lots one purchaser can buy, and on the share sold to foreign purchasers
Lenders then compare the value of qualifying presales with the debt. Using the example above, a lender asking for presales equal to 100 per cent of a $6.0 million facility would want about six of the ten townhouses sold, before allowing for GST and selling costs. A lender asking for 50 per cent cover would want about three.
Does APRA require a minimum level of presales?
APRA does not require a minimum level of presales, and it has never set one. A presale requirement is the policy of the individual lender.
The confusion comes from a letter. On 7 March 2017, after a thematic review of commercial property lending carried out during 2016, APRA wrote to all authorised deposit-taking institutions (ADIs). Among its observations on residential development lending, the letter said that some ADIs had tightened presale criteria and that ADIs were "now generally requiring qualifying presales equivalent to at least 100 per cent of committed debt". Many in the market came to treat that figure as a regulatory rule.
In February 2025 APRA wrote to ADIs again to correct that reading. The letter states that the 2017 reference "does not represent a minimum requirement or expectation of APRA" and that it reflected industry practice observed at the time of the review. APRA's requirements and guidance for credit risk sit in Prudential Standard APS 220 and Prudential Practice Guide APG 220, and the letter confirms that APRA has not set minimum requirements or expectations for presales in either. APRA added that presales still have an important role in sound credit risk management.
What this means for you. A bank may still ask for presales, including cover equal to the whole debt, as its own credit policy. It cannot accurately describe that as an APRA rule. Policy differs between banks and between projects, so a presale hurdle at one lender is not the final word.
APRA supervises ADIs such as banks. Non-bank and private lenders are not ADIs and set presale policy by their own risk appetite and that of their funders.
How can you fund a project with fewer presales or less equity?
You can fund a project with fewer presales or less equity by choosing a lender whose policy allows it, by adding a second layer of funding, or by changing the project so the numbers fit. Each option has a cost.
- Non-bank senior lenders. Many fund construction with low or no presales and accept higher LTC, in return for a higher margin and fees. The comparison of bank, non-bank and private lenders explains why their policies differ.
- Mezzanine finance. A second-ranking loan can cover part of the equity gap if the senior lender consents. See the guide to mezzanine finance for the structure and risks.
- Staging. Building in stages cuts peak debt, so fewer presales are needed to cover it.
- Planning for the tail. A project funded without presales is more likely to complete with unsold lots, so allow for the cost of a residual stock loan in the feasibility.
A lower presale hurdle lets you start sooner, but it leaves more sales risk with you and your guarantors. Test the feasibility at lower prices and a longer selling period before you accept higher leverage.
A commercial finance broker can set your LTC, GRV LVR and presale position against the policies of several lenders at once. To have a broker partner review your feasibility, send it through the enquiry form. This site is not a lender and does not give credit advice.
Frequently asked questions
What is a good loan to cost ratio for a development?
There is no single good figure. As a general guide, many banks lend around 65 to 80 per cent of total development cost and some non-bank lenders lend more. A lower ratio means more of your own money in the project, a lower interest bill and usually a better price. The right level depends on your margin and cash reserves.
Is GRV calculated with or without GST?
Most development lenders measure gross realisable value net of GST, and some also take off selling costs to arrive at a net realisable value. Practice is not uniform, so confirm the definition in the term sheet. Comparing one lender's ratio on a net figure with another's on a GST-inclusive figure will give a misleading picture.
How many presales do you need for a development loan?
It depends on the lender. Some banks ask for qualifying presales covering a large share of the debt, in some cases all of it, while many non-bank lenders fund with few or none at a higher price. There is no minimum set by APRA or by law, so the number is a matter of each lender's credit policy.
Did APRA require 100 per cent presales?
No. APRA's March 2017 letter to banks observed that they were generally requiring presales of at least 100 per cent of committed debt. In February 2025 APRA wrote again to say this was a reflection of industry practice at the time and does not represent a minimum requirement or expectation of APRA.
Do presales to overseas buyers count as qualifying presales?
Often only up to a limit. Many lenders cap the share of qualifying presales that can be to foreign purchasers, because they see a higher risk that those buyers will not obtain finance and settle. The cap and the definition of a foreign purchaser are set by each lender, so check the presale conditions before you launch a marketing campaign.
Does land I already own count as equity in a development?
Yes, the value of the land above any debt secured on it normally counts toward your equity contribution. Lenders decide whether to recognise the purchase price or the current valuation, and banks in particular can be cautious about relying on a large uplift in land value in place of cash equity.
Sources
Written by
Development and private lending writer
Thandiwe covers development finance and the private lending market. She writes about how facilities are sized and drawn, what an exit strategy has to prove, and the warning signs in short-term loan offers, with the aim that readers understand the cost of a deal before they sign it.