Key facts
- What it funds
- Site acquisition, construction and residual stock
- How it is sized
- Lower of loan to cost and loan to GRV limits
- Typical term
- Commonly 12 to 36 months, matched to the build
- Drawdowns
- Progressive, certified by a quantity surveyor
- Interest
- Usually capitalised within the facility limit
- Repayment
- Sales, refinance or a residual stock loan
What is development finance and how does it differ from a commercial property loan?
Development finance is a short-term commercial facility that funds the cost of buying a site and building a project, and it is repaid from the sale or refinance of the finished product rather than from rent. The lender advances money in stages as work is completed, so the debt grows as the project grows in value. It sits within the wider family of commercial loans, but it is assessed differently to almost every other product.
A standard commercial property loan is secured against a building that already exists and already earns, or could earn, rent. Development finance is secured against something that is not finished, so the lender is underwriting your feasibility, your builder and your exit as much as the land.
| Feature | Development finance | Standard commercial property loan |
|---|---|---|
| Security | The site plus work in progress, valued on an "as if complete" basis | An existing, completed property |
| How the loan is sized | Loan to cost and loan to gross realisable value | LVR against current market value, plus interest cover |
| Drawdown | Progressively, against certified work | One lump sum at settlement |
| Interest | Usually capitalised into the facility | Paid monthly from rent or business cash flow |
| Term | Commonly 12 to 36 months, matched to the build program | Commonly 3 to 30 years, lender dependent |
| Repayment | Sales, refinance or a residual stock loan | Principal and interest or interest only, from income |
| Monitoring | A quantity surveyor report with every claim | Periodic review |
Consumer credit law usually does not apply. Most development finance is written to a company or a trust with a corporate trustee for a business purpose. ASIC's guidance is that loans to companies are not subject to the national consumer credit legislation, so responsible lending obligations and other consumer credit protections generally do not apply. An individual borrowing mainly to build residential investment property can be in a different position. Have your solicitor confirm which rules cover your loan.
What projects and stages does development finance fund?
Development finance funds projects where value is created by subdividing or building, from a two lot subdivision to a multi-level apartment building.
Project types
- Townhouses and duplexes. These are the most widely funded projects. Build programs are short, the product suits owner occupiers and many lenders will consider them with few or no presales.
- Apartments. These have longer programs, larger debt and a single completion date for every unit, so lenders look hardest at presales, the builder's balance sheet and settlement risk.
- Land subdivision. The facility funds civil works, services and titles rather than buildings.
- Commercial and industrial builds. Warehouses, strata industrial units, offices, medical and childcare centres are funded on the same principles. A signed agreement for lease with a sound tenant can do the job that presales do in a residential project, and how lenders assess a commercial lease matters as much as the build.
Stages funded
- Site acquisition. A land loan buys or refinances the site, often before the development approval is final. Leverage against raw land is lower than against a funded build.
- Construction. The main facility pays the builder, consultants, statutory charges and usually interest. This stage is covered in detail in the guide to construction finance.
- Residual stock. If some lots are unsold at completion, a separate loan against the finished stock can repay the construction facility while the remaining sales are made.
How much can you borrow with development finance?
The amount you can borrow with development finance is the lower of two limits: a percentage of total development cost and a percentage of gross realisable value. The first test protects the lender if costs blow out, and the second protects it if end values fall.
- Loan to cost (LTC or LCR). The facility limit divided by total development cost, which includes land, construction, consultants, statutory fees, contingency and finance costs. As a general guide, many banks lend 65 to 80 per cent of cost and some non-bank lenders go higher at a higher price.
- Loan to gross realisable value (GRV). The facility limit divided by the valuer's estimate of total sale proceeds on completion, usually net of GST. Many lenders work in a range of about 60 to 70 per cent, and policy varies by lender, location and product.
Whatever the lender does not fund is your equity contribution. Equity can be cash, or the value of land you already own above its debt, and lenders almost always require it to be spent before the first drawdown. APRA has told banks it expects them to ensure a sufficient level of "hard equity" is at risk from sponsors, which is why a bank will discount equity that comes from an optimistic uplift in land value.
If you cannot fund the whole gap, mezzanine finance can sit behind the senior lender and cover part of it, subject to the senior lender's consent.
Presales
Presales are unconditional contracts to buy the finished lots, signed before or during construction. Some lenders, mainly banks, want presales that cover a set share of the debt before they will fund the build, while many non-bank lenders fund with few or none and charge more for the added sales risk.
APRA has never set a minimum presale level. In February 2025 it wrote to banks to confirm that a figure in its March 2017 letter described industry practice at the time and was not an APRA requirement. The detail, with a worked example, is in the guide to presales, LVR and loan to cost.
How do progressive drawdowns and capitalised interest work?
Progressive drawdowns mean development finance is released in instalments as work is completed, not as a lump sum. Each month the builder issues a progress claim, and the lender's quantity surveyor (QS) inspects the site and certifies the value of work done and the cost to complete.
The lender pays the certified amount only if the undrawn balance of the facility is still enough to finish the project. If it is not, you are asked to put in more equity before the next payment is made.
Capitalised interest means the interest on each drawdown is added to the loan balance instead of being paid from your pocket each month. The lender sets aside an interest allowance inside the facility limit, based on the build program and a sales period. Capitalising preserves your cash, but it also means interest is charged on interest, and a delay uses up the allowance faster than planned.
What does development finance cost?
Development finance costs more than a standard investment loan because the lender is carrying construction, sales and timing risk on an unfinished asset. Pricing is set deal by deal, so compare the total cost over the life of the project and not the headline rate.
- Interest margin. A margin over a base or reference rate, charged on the drawn balance. It moves with leverage, presales, location, project size, your experience and the type of lender.
- Line fee. A percentage charged on the whole facility limit, drawn or undrawn, and common with banks. A low margin with a line fee can cost more than a higher all-in rate early in the build, when little is drawn.
- Establishment fee. A one-off fee on the facility limit, usually deducted from the first drawdown.
- QS and valuation fees. You pay for the initial valuation, the initial QS report and a QS inspection for every progress claim.
- Legal and other fees. You pay the lender's legal costs as well as your own. Some private lenders also charge exit or discharge fees, so read the letter of offer line by line.
The commercial loan calculator can help you test how a change in rate or term affects interest on a given balance.
What do lenders want to see before approving development finance?
Lenders want evidence that the development finance can be repaid from a project that is approved, costed, deliverable and profitable. A complete submission normally includes the following.
- A feasibility study. A line by line budget showing land, construction, professional fees, statutory charges, contingency, finance and selling costs against expected sales. Lenders look for a profit margin that leaves room for error, commonly 15 to 20 per cent on cost or more as a general guide.
- Development approval or a planning permit. Construction funding normally needs the DA or permit in place, with stamped plans and any conditions addressed.
- A fixed price building contract. Lenders prefer a lump sum contract on standard industry terms with a licensed builder, because it moves most cost risk away from you.
- Builder due diligence. The lender reviews the builder's licence, insurance, financial statements, current workload and completed projects of similar size.
- Developer experience. A record of similar completed projects is a major pricing and approval factor. First time developers are often asked for more equity, an experienced project manager or a stronger builder.
- Financial position. Statements of assets and liabilities for the guarantors, entity structure documents and evidence of where the equity is coming from.
- Sales evidence. Presale contracts and deposits held, the marketing plan, and for commercial projects any agreement for lease.
Should you use a bank, non-bank or private development lender?
The right development lender depends on your presales, equity, experience and how quickly you need to start. Banks are the cheapest source of development finance and the hardest to qualify for, while non-bank and private lenders accept more risk for a higher return.
| Lender type | Typical strengths | Typical trade-offs |
|---|---|---|
| Bank | Lowest cost of funds, suited to experienced developers with presales and a strong builder | Lower leverage, presale and experience hurdles, slower credit process |
| Non-bank lender | Higher leverage, fewer or no presales, more flexible on structure and project type | Higher margin and fees, close monitoring |
| Private lender | Fast decisions, short terms, useful for land settlements, small projects and complex situations | Highest cost, short terms, heavy reliance on a clear exit |
The comparison of bank, non-bank and private lenders sets out how each type is funded and regulated.
How is development finance repaid at the end of the project?
Development finance is repaid through one of three exits: selling the finished lots, refinancing into long-term debt, or moving unsold lots onto a residual stock loan. Lenders assess the exit before they approve the facility, and the loan term is set to allow for it.
- Sales. Presale contracts settle after titles are registered and occupancy certificates issue. The lender takes the net proceeds until the debt is cleared, then releases the rest to you.
- Refinance to an investment loan. If you plan to keep some or all of the project, the completed property is revalued and refinanced on normal investment terms, serviced by rent.
- A residual stock loan. Where a handful of lots remain unsold near expiry, a residual stock loan repays the construction lender and gives you time to sell without discounting.
If the facility is about to expire before any of these is ready, short-term bridging finance is sometimes used, at a cost that eats into profit. GST applies to sales of new residential premises and affects your net proceeds, so have your accountant model it before you set prices.
What are the main risks of development finance?
The main risks of development finance are cost overruns, delays, builder insolvency and a lower valuation on completion, and each one can force you to find more equity at short notice.
- Cost overruns. Variations, latent site conditions and price rises outside the contract must be funded by you, because the lender will not pay a claim that leaves the project short of the cost to complete.
- Delays. Weather, approvals, labour shortages and authority connections extend the program. Every extra month adds capitalised interest and can push the project past the facility expiry or presale sunset dates.
- Builder insolvency. If the builder fails mid project, work stops, subcontractors may be unpaid and a replacement builder will price in the risk. Builder due diligence and retention reduce the exposure but do not remove it.
- Valuation on completion. If the market falls during the build, purchasers may struggle to obtain their own finance and settle, and a refinance or residual stock loan will be sized on the lower values.
- Personal exposure. Directors normally give personal guarantees, so a shortfall in the project can reach your other assets.
How long does development finance take to arrange?
Development finance commonly takes several weeks to a few months to arrange from first submission to first drawdown, depending on the lender and how complete your documents are. Private lenders can move faster and banks usually take longer. Nobody can guarantee a timeframe.
- Feasibility and lender selection. Your submission is prepared and matched to lenders whose policy fits the project.
- Indicative terms. A lender issues a non-binding term sheet setting out limit, pricing and conditions.
- Valuation and QS review. The lender commissions an "as is" and "as if complete" valuation and an initial QS report on the budget and contract.
- Credit approval and documents. A formal letter of offer is issued, then mortgages, guarantees and the builder's side deed are signed.
- Conditions precedent. Equity is confirmed as spent, insurances and approvals are checked, and the first drawdown is made.
Because policy differs so much between lenders, many developers use a commercial finance broker to test the project with several of them at once. You can send the outline of your project through the enquiry form and it will be passed to a broker partner. This site is not a lender and does not give credit advice.
Frequently asked questions
Is a property development loan the same as construction finance?
Not quite. A property development loan can cover the whole project: buying the site, building and holding unsold stock at the end. Construction finance is the part of the facility that pays for the build itself, drawn progressively against certified work. Many lenders write both under one facility, while others fund the land and the construction separately.
Can a first time developer get development finance?
Yes, some lenders fund first time developers, but usually on tighter terms. Expect to be asked for more equity, a fixed price contract with an established builder, and often an experienced project manager or development partner. Smaller projects such as duplexes and townhouses are the usual starting point. Approval is never guaranteed and policy varies widely by lender.
How much equity do you need for a property development?
It depends on the lender's loan to cost limit. As a general guide, if a lender funds 65 to 80 per cent of total development cost, you need the remaining 20 to 35 per cent as cash or as equity in land you already own. Some non-bank lenders fund more, and mezzanine finance can cover part of the gap at a higher price.
Do you need presales to get a development loan?
Not always. Presales are a lender policy and not a legal requirement, and APRA confirmed in February 2025 that it has not set a minimum presale level for banks. Banks commonly ask for presales covering a share of the debt, while many non-bank lenders fund projects with few or no presales in return for a higher margin or lower leverage.
Is interest paid monthly on a development loan?
Usually not from your own cash. Most development facilities capitalise interest, which means each month's interest is added to the loan balance and paid from an allowance inside the facility limit. The total debt, including capitalised interest and fees, is then cleared from sale proceeds or a refinance when the project completes.
What happens if a development project goes over budget?
You are normally required to fund the overrun yourself. Before each drawdown the quantity surveyor checks that the undrawn facility still covers the cost to complete. If it does not, the lender stops paying claims until you add equity. A realistic contingency in the budget and a fixed price building contract are the main protections.
Sources
- APRA: Letter to ADIs clarifying its March 2017 letter regarding commercial property lending (February 2025)
- APRA: Letter to all ADIs, Commercial property lending thematic review observations (7 March 2017)
- ASIC: FAQs, Does the credit legislation apply?
- ATO: Building and construction, residential premises
Written by
Development and private lending writer
Thandiwe covers development finance and the private lending market. She writes about how facilities are sized and drawn, what an exit strategy has to prove, and the warning signs in short-term loan offers, with the aim that readers understand the cost of a deal before they sign it.
Last reviewed 24 November 2026. See how we research and check our guides on the editorial team page.
This page is general information, not credit, tax or financial advice. Figures describe typical market practice and are not quotes. See our disclaimer.